Work is progressing well and over the last month we’ve delivered fibre in Bradley Stoke, Chipping Sodbury, Coalpit Heath, Codrington, Dodington, Dyrham, Elberton, Hallen, Hinton, Olveston, Siston Hill, parts of Kingswood, Tytherington and Westerleigh.
Residents can now place orders with their chosen Internet Service Provider (ISP) to see what broadband speeds and packages are available to them.
Important: Not all premises within these postcodes will get fibre as part of this phase of work and broadband speeds will not automatically improve. Individual householders should check options via the Openreach website and where appropriate contact their chosen ISP directly. There are useful sources of information to guide you through this process on our website
Don’t worry, it’s coming
We need to close a road to deliver broadband to some parts of Codrington. This is currently being organised and we anticipate completing deployment in Codrington by the end of February 2018.
Similarly, in Sodbury Common we have encountered additional work required on some ducting, which has delayed full rollout. This work is due to be completed very shortly.
Phase 3: broadband is coming to even more areas
Last July, we secured additional investment to bring ultrafast and Next Generation Access broadband to approximately 4,300 additional homes and businesses in South Gloucestershire by the end of 2018.